In a judgment that clarifies
decades of confusion surrounding the implementation of welfare legislation for
construction workers, the Supreme Court of India has delivered a decisive
verdict. The case, involving the National Highways Authority of India (NHAI)
and several contractors, revolved around a critical question: Can a law that
exists on paper but is not implemented on the ground be considered “subsequent
legislation” under a commercial contract?
This blog post breaks down the
complex legal issues, the Court’s reasoning, and the far-reaching implications
of this ruling for government authorities, public sector undertakings, and
contractors across the country.
I. The Heart of the Dispute:
Paper Law vs. Implemented Law
The conflict stemmed from two
pivotal welfare enactments:
1. The Building and Other Construction Workers
(Regulation of Employment and Conditions of Service) Act, 1996 (BOCW Act):
Designed to regulate employment and ensure safety, health, and welfare for
construction workers.
2. The Building and Other Construction Workers’
Welfare Cess Act, 1996 (Cess Act): Levies a cess (1-2%) on construction
costs to fund the Welfare Boards established under the BOCW Act.
While these laws were technically
notified in 1995-1996, a shocking reality emerged: they remained largely
unimplemented for years. State governments failed to constitute the mandatory
Welfare Boards, frame necessary rules, or establish the machinery for cess
collection. It took persistent intervention and monitoring by the Supreme Court
itself, starting in 2008, to prod states into action.
Against this backdrop, the NHAI
entered into contracts with various contractors for national highway projects.
Standard NHAI contracts contained two crucial clauses:
a. Clause 14.3: Required bidders to include
all duties, taxes, and levies payable as of 28 days before the bid submission
date in their quoted prices.
b. Clause 70.8 (“Subsequent Legislation”):
Provided that if a new law or change in law after the bid date caused
additional cost, the contractor would be reimbursed.
When states like Uttar Pradesh,
Jharkhand, and Odisha finally began implementing the BOCW Act and levying cess
years after contracts were signed, NHAI deducted these amounts from
contractors’ bills. The contractors argued this cess levy was “subsequent
legislation” under Clause 70.8, entitling them to reimbursement. NHAI contended
the laws were already on the statute book when bids were submitted, so the cost
should have been factored into the original bid price.
Arbitral tribunals unanimously
ruled in favour of the contractors. NHAI challenged these awards in court,
leading to the present appeals before the Supreme Court.
II. The Core Legal Question
The Supreme Court framed the
essential issue as follows:
For the purposes of a commercial
contract, does a welfare legislation like the BOCW Act “come into force” on the
date it is notified in the Gazette, or on the date when the requisite machinery
(Welfare Boards, rules, collecting officers) is actually established to give it
practical effect?
III. The Supreme Court’s Detailed Reasoning
The Court’s judgment, authored by
Justice Sanjay Kumar, methodically dismantled NHAI’s arguments and upheld the
arbitral awards. The reasoning rested on several key pillars:
1. Statutory Scheme is Incomplete Without
Implementation Machinery
The Court meticulously examined
the intertwined scheme of the BOCW and Cess Acts. It highlighted that the Cess
Act’s very purpose, as stated in its preamble, is to “augment the resources of the
Welfare Boards constituted under the [BOCW Act].” Therefore, the levy of cess
is intrinsically linked to the existence of a Welfare Board. Collecting cess
without a Board to receive and utilize it would alter its character from a
dedicated “fee” to a general “tax,” potentially undermining the law’s validity.
2. A Law is Dormant Until Executed
The Court took judicial notice of
the “sorry state of affairs” documented in its own earlier orders in National
Campaign Committee v. Union of India. It emphasized that despite being notified
in the mid-1990s, the Acts “just remained on paper” due to governmental
inertia. A law, especially one requiring the creation of administrative bodies,
cannot be said to be operative for contractual purposes when the state has
taken no steps to execute it. The Court poignantly noted that putting the Cess
Act into force (1995) before the parent BOCW Act (1996) was a case of “putting
the cart before the horse.”
3. Precedents Support Practical Operability
The Court relied on its earlier
decisions to solidify this principle:
a. In Dewan Chand Builders & Contractors v.
Union of India, it had observed that the Cess Act and Rules became “operative”
in Delhi only in January 2002 when the Rules were notified and the Board was
constituted, not in 1996.
b. In A. Prabhakara Reddy & Co. v. State of
M.P., it held that the constitution of the Welfare Board is a condition
precedent for the levy and collection of cess. While registration of workers or
provision of welfare benefits can follow later, the Board must first exist.
4. Limited Scope of Judicial Interference in
Arbitration
The Court reaffirmed the settled
law on the restricted role of courts in reviewing arbitral awards under
Sections 34 and 37 of the Arbitration and Conciliation Act, 1996. A court does not
sit in appeal. Interference is permitted only on grounds like patent
illegality, violation of public policy, or if the award is so perverse that no
reasonable person could arrive at it.
The Court held that interpreting
whether an event qualifies as “subsequent legislation” under Clauses 14.3 and
70.8 is primarily a matter of contract construction, squarely within the
arbitrator’s domain. Since the arbitral tribunals’ view—that the effective
implementation date triggered the “subsequent legislation” clause—was a plausible
and possible interpretation, it was not open for the Court to substitute its
own view.
5. The “Factoring-In” Argument is Logically
Flawed
The Court rejected NHAI’s
argument that contractors should have foreseen and included the cess cost in
their 2001-2005 bids. It held that asking a contractor to factor in a levy for
which there was no collection machinery, no designated payee (Welfare Board),
and no certainty of implementation would lead to “unjust and unlawful
enrichment.” A bidder cannot price a hypothetical liability that may or may not
materialize years later.
IV. Case-by-Case Application & Findings
The Court applied these
principles to each appeal:
a. Prakash Atlanta (JV) – C.A. No. 4513 of
2025: Contract signed in 2001, terminated in 2008. Uttar Pradesh notified
rules effective Feb 2009. NHAI first sought to deduct cess in 2012, during
execution proceedings, despite never raising it in prior arbitration. The Court
found this an “afterthought” and “clutching at straws” to reduce its liability.
Allowed. NHAI must release the deducted amount.
b. Gammon-Atlanta (JV) – C.A. No. 5416 of 2025:
Bid in 2000, Orissa notified rules and constituted Board in 2008. Dismissed.
c. PCL Suncon (JV) – C.A. No. 5302 of 2025:
Bid in 2001, Jharkhand rules came in 2007. Dismissed.
d. NKG Infrastructure Ltd. – C.A. No. 5301 of
2025: Bid in Dec 2008, Uttar Pradesh notification in Feb 2010. Dismissed.
e. Hindustan Construction Co. Ltd. – C.A. No.
5304 of 2025: Bid in 2005, Uttar Pradesh notification in 2010. Dismissed.
f. DIC-NCC (JV) – C.A. No. 5412 of 2025:
Bid in Dec 2003, Gujarat constituted an ad-hoc Board in Dec 2004. Dismissed.
V. Key Conclusions and Directives
The Supreme Court summarised its
conclusions as follows:
1. The BOCW and Cess Acts were brought into
force on their notified dates but remained dormant until Welfare Boards were
constituted.
2. The Cess Act is complementary to the BOCW
Act. Without a Welfare Board, levy and collection of cess cannot logically
arise.
3. The constitution of a Welfare Board is a condition
precedent for giving effect to the cess levy.
4. Mere mention of the Acts in a contract (like
Clause 34.2) has no significance if the requisite machinery for implementation
is absent.
5. The arbitral tribunals’ interpretation of the
“subsequent legislation” clause was plausible and justified. The awards were
not perverse, patently illegal, or against public policy.
6. Courts cannot interfere with an arbitral
award merely because an alternative view of the contract is possible.
VI. Implications and Takeaways
This landmark judgment has profound
implications:
For Government Authorities
& PSUs (like NHAI):
a. They cannot hide behind the technical
notification date of a law to impose financial liabilities retroactively on
contractors when they themselves failed to implement the law for years.
b. The decision underscores the duty of the
state to actively implement welfare legislation. Lethargy has contractual and
financial consequences.
c. Deduction at source under cess rules
presupposes the existence of the machinery (Welfare Board) to receive the
funds.
For Contractors:
a. Provides significant relief and clarity on
liability for cess levied long after contract signing.
b. Reinforces the sanctity of “change in law”
or “subsequent legislation” clauses in government contracts.
c. Highlights the importance of precise
contractual language regarding the allocation of statutory liability.
For Arbitration Law:
a. Strongly reaffirms the principle of minimal
judicial intervention in arbitral awards, especially on matters of contract
interpretation.
b. Clarifies that a “plausible view” taken by
an arbitrator, even on a mixed question of fact and law, is virtually immune to
challenge.
For Social Welfare
Jurisprudence:
The Court has indirectly enforced the implementation of worker welfare
laws by linking their “operative” date to tangible action by the state, not
mere legislative enactment.
Final Thought
The Supreme Court’s judgment cuts
through legal formalism to focus on practical reality. It establishes that for
a law to create enforceable obligations in the commercial world, it must be
more than text in a statute book; it must be a living, operative framework.
This ruling not only settles a long-standing contractual dispute but also
serves as a reminder that the state’s responsibility extends beyond passing
laws to effectively executing them.
Judgment Name: Prakash
Atlanta (JV) vs. National Highways Authority of India & Connected Appeals
(Civil Appeal Nos. 4513, 5301, 5302, 5304, 5412 & 5416 of 2025), Supreme
Court of India, decided on January 20, 2026.
0 Comments