A Second Chance for Justice: The Supreme Court Clarifies Power to Extend Arbitrator’s Mandate Post-Award

Supreme Court

In a significant ruling that harmonizes statutory timelines with the overarching goal of dispute resolution, the Supreme Court of India, on February 3, 2026, delivered a crucial judgment in C. Velusamy v. K Indhera. The Court addressed a vexing procedural deadlock: Can a court grant an extension of an arbitrator’s mandate under Section 29A of the Arbitration and Conciliation Act, 1996, after the arbitrator has already rendered an award, but did so after the statutory deadline had expired? In reversing the Madras High Court, the Supreme Court answered in the affirmative, prioritizing the completion of the arbitral process over a rigid, technical forfeiture. This blog post delves into the Court’s reasoning, the statutory landscape, and the profound implications of this ruling for the efficiency and integrity of arbitration in India.

 I. The Procedural Conundrum: A Null Award and a Timely Application

The dispute originated from three agreements to sell between the parties. Following disagreements, a sole arbitrator was appointed by the Madras High Court on April 19, 2022.

The Critical Timeline:

a. Commencement of 12-month period: Pleadings were completed on August 20, 2022, triggering the 12-month clock under Section 29A(1) for making the award.

b. Consensual Extension: Before this period lapsed, the parties jointly extended the mandate by a further six months under Section 29A(3), making the new deadline February 20, 2024.

c. Post-Deadline Award: Despite hearings concluding and the matter being reserved for award in September 2023, the arbitrator, after several adjournments related to settlement talks, finally signed the award on May 11, 2024 – nearly three months after the mandate had technically terminated.

d. Dueling Applications: The respondent, aggrieved by the award, filed an application under Section 34 to set it aside, arguing it was a nullity as the mandate had expired. Conversely, the appellant filed an application under Section 29A(5) seeking an extension of the arbitrator’s mandate nunc pro tunc (now for then).

The Madras High Court, in its order dated January 24, 2025, held that an application under Section 29A was not maintainable once an award had been passed. It followed the view that an award rendered after the expiry of the mandate is a nullity, and the court possessed no power to resuscitate a terminated mandate post-award. This appeal challenged that narrow interpretation.

 II. The Core Legal Question

The Supreme Court framed the pivotal question of law for its consideration:

Whether a Court can entertain an application under Section 29A(5) of the Arbitration and Conciliation Act, 1996 to extend the mandate of the arbitrator(s) for making the award even after an 'award' is rendered, though after the expiry of the statutory limit of eighteen-month period?

The answer to this question required a deep dive into the evolution of arbitration law, the legislative intent behind Section 29A, and the fundamental principles of access to justice.

 III. The Evolution of Timelines: From the 1940 Act to the 1996 Act

To appreciate the import of Section 29A, the Court first traced the historical treatment of timelines in arbitration law.

Under the Arbitration Act, 1940:

The 1940 Act, in its First Schedule, prescribed a four-month period for making an award. Crucially, Section 28 of the 1940 Act granted the court an unambiguous, wide power:

> "The Court may, if it thinks fit, whether the time for making the award has expired or not and whether the award has been made or not, enlarge from time to time the time for making the award."

This provision explicitly authorized the court to extend time even after an award had been made, reflecting a clear intent to salvage the arbitral process from technical failure.

Under the Original 1996 Act:

The 1996 Act, modeled on the UNCITRAL Model Law, initially embraced party autonomy and minimal judicial intervention to an extreme. It conspicuously omitted any statutory timeline for rendering an award. The only recourse for inordinate delay was an application for termination of the arbitrator’s mandate under Section 14. This omission, as the Court noted, led to unintended consequences—arbitrations dragging on for years without any procedural impetus for conclusion, thus defeating the very objective of arbitration as a speedy alternative to litigation.

 IV. The Legislative Cure: Introduction of Section 29A

The pathology of indefinite delays prompted reform. The Law Commission of India, in its 176th Report, diagnosed the problem and recommended a structured yet flexible timeline system. The Commission’s philosophy was clear: the goal was not to terminate arbitrations but to compel their timely progress and ensure they reach a final award. The report emphasized that even if delays occurred, "there is no point in terminating the arbitration proceedings... We propose it as they should be continued till award is passed." This was to avoid wastage of time, costs, and evidence already led.

Based on these recommendations, Section 29A was introduced via the 2015 Amendment Act (with retrospective effect) and later refined in 2019. Its architecture is as follows:

a. 29A(1): Mandates an award within 12 months of completion of pleadings.

b. 29A(3): Allows parties, by consent, to extend by a further 6 months.

c. 29A(4): States that if the award is not made within the above periods, the mandate "shall terminate". However, this termination is subject to the power of the Court to extend the period, which power can be exercised "either prior to or after the expiry of the period so specified".

d. 29A(5): Allows any party to apply for an extension, grantable by the Court only for "sufficient cause."

e. Proviso to 29A(4): Importantly, it states that where an application under sub-section (5) is pending, the mandate of the arbitrator shall continue till the disposal of the said application. This creates a statutory "holding pattern."

f. 29A(6) & (7): Empowers the Court, while extending time, to substitute arbitrators. The reconstituted tribunal is deemed to be in continuation of the previous one, proceeding from the existing stage and record.

 V. Demystifying "Termination" and the Court's Unimpaired Power

The High Court’s interpretation hinged on viewing the "termination" of the mandate under Section 29A(4) as absolute and final, especially once an award was passed. The Supreme Court dismantled this reading.

The Court, building upon its precedent in Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., clarified that the termination under Section 29A(4) is not "stricto sensu" (in the strict sense). It is conditional and transitory, subject to the court's power to revive it via extension. The word "terminates" in this context does not reflect a final, legal death of the proceedings but a suspension that awaits the court's intervention.

The Court made several key interpretive findings:

1.No Bar Post-Award: Section 29A does not contain any explicit bar against filing an extension application after an award is rendered. The absence of such a prescription is significant.

2.Status of a Post-Expiry Award: An award made after the mandate has expired is not a valid, enforceable award. The Court aptly termed it "non est" (as if it did not exist) or, more precisely, an award that is unenforceable under Section 36. It need not even be set aside under Section 34; it simply carries no legal force.

3.Indiscretion of Arbitrator vs. Power of Court: The arbitrator’s unilateral act of passing an award without a valid mandate is an indiscretion. This indiscretion cannot "denude the power and jurisdiction" statutorily vested in the Court. The Court’s power under Section 29A is independent and superior to the arbitrator’s procedural misstep. To hold otherwise would allow an arbitrator’s error to frustrate the entire statutory scheme and the parties’ investment in the arbitration.

4.The Phrase "If an Award is Not Made": The Court interpreted the conditional phrase in Section 29A(4) – "If the award is not made within the period specified..." – as describing the trigger for the termination provision. It is not addressing the scenario where an award has been belatedly rendered. The section’s focus is on enabling the court to extend time "prior to or after the expiry," irrespective of what the arbitrator may have done in the interim.

5.Toolkit of Judicial Control: The Court highlighted that Section 29A arms the court with a versatile "toolkit" to ensure disciplined and efficient proceedings, even when extending time retrospectively:

a. Costs: Imposing actual or exemplary costs on parties (S. 29A(8)).

b. Fee Reduction: Reducing the arbitrator’s fees by up to 5% per month for delay attributable to them (Proviso to S. 29A(4)).

c. Substitution: Replacing one or all arbitrators if the situation warrants (S. 29A(6)).

d. Terms & Conditions: Imposing specific terms while granting extension for "sufficient cause" (S. 29A(5)).

 

This arsenal ensures that the power of extension is not a mere rubber stamp but a disciplined, corrective mechanism. The fear that a post-award extension would foster a culture of indifference to timelines is mitigated by these deterrent and corrective measures at the court’s disposal.

 VI. The Constitutional Imperative: Effective Access to Justice

Beyond textual interpretation, the Supreme Court anchored its judgment in a broader constitutional principle of access to justice. The Court stated that a constitutional court has an obligation to ensure that a legal remedy is:

a. Accessible (easily available),

b. Affordable (reasonably priced),

c. Expeditious (devoid of unreasonable delays), and

d. Cohesive (forming a complete and effective whole).

A hyper-technical interpretation that forever forecloses the arbitral process due to a missed deadline—especially where parties have invested substantial time and resources—would render the remedy incohesive and ineffective. It would force parties to either abandon their claim or restart litigation from scratch, violating the principles of affordability and expeditiousness. Section 29A, interpreted purposively, is designed to be a cohesive mechanism that shepherds disputes to a final resolution.

 VII. International Perspectives: A Pragmatic Consensus

The Court bolstered its view by surveying international jurisprudence, finding a general judicial reluctance to invalidate awards solely on grounds of delay, especially where no prejudice is shown.

 

a. England: Both the old Arbitration Act 1950 (Section 27) and the current 1996 Act (Section 50(4)) allow courts to extend time "whether or not the time previously fixed (by agreement or otherwise) has expired." The English Court of Appeal in Oakland Metal Co Ltd. confirmed this wide, retrospective discretion.

b. Mauritius: The Privy Council in Alphamix Ltd. upheld an award issued three days late, finding the parties had tacitly agreed to the short delay.

c. Commentaries: Authorities like Redfern and Hunter note that courts in many jurisdictions are reluctant to invalidate a late award where a party uses the time limit tactically to frustrate the arbitration. The ICC Rules also provide for the extension of time limits and revival of a tribunal’s mandate.

This international perspective underscores a shared pragmatic approach: arbitration agreements are for resolving disputes, and procedural deadlines should not become traps that destroy that very purpose absent bad faith or prejudice.

 VIII. The Supreme Court’s Conclusions and Directives

Synthesizing its analysis, the Supreme Court laid down the following principles:

1.Maintainability: An application under Section 29A(5) for extension of the arbitrator’s mandate is maintainable even after the expiry of the statutory period (12+6 months) and even after the arbitrator has rendered an award during the period of lapsed mandate.

2.Status of Award: Such a belatedly rendered award is ineffective and unenforceable (non est). Its existence does not impair the court’s jurisdiction to consider the extension application.

3.Court’s Discretionary Exercise: When such an application is made, the court must examine whether "sufficient cause" exists for the delay. It is not an automatic extension. The court must scrutinize the reasons for the delay, attributing blame where due.

4.Use of Corrective Tools: In deciding the application, the court must consider employing the corrective measures in its toolkit:

a. Reduce the arbitrator’s fees if delay is attributable to them.

b. Impose costs (actual or exemplary) on parties if warranted.

c. Consider substituting the arbitrator(s) if the facts demand (though this is not mandatory).

d. Impose specific terms and conditions for the concluded proceedings.

5.Continuation of Proceedings: If the mandate is extended, the arbitral tribunal (whether the original or a substituted one) will seamlessly continue the proceedings from the exact stage where the mandate expired, based on the existing record. The deeming provisions under Sections 29A(6) & (7) facilitate this continuity.

Outcome: The Supreme Court allowed the appeal, set aside the Madras High Court’s order, and restored the appellant’s Section 29A application (No. 5993 of 2024) for fresh disposal in accordance with the principles laid down in this judgment.

 IX. Implications and Analysis: A Balanced and Progressive Ruling

The Velusamy judgment is a masterclass in balanced statutory interpretation. It achieves several important objectives:

1. Prioritizes Substance Over Form: The ruling refuses to let a procedural default (the late award) extinguish substantive rights. It recognizes that arbitration is a contractual investment, and its collapse on a technicality represents a significant injustice.

2. Empowers Courts as Supervisory Facilitators: It reaffirms the court’s role under the 1996 Act not as an intruder but as a facilitator and supervisor tasked with ensuring the efficacy of the alternative dispute resolution mechanism. The court’s power under Section 29A is curative and completive, not destructive.

3. Introduces Disciplined Flexibility: By clarifying that extension is not automatic and must be accompanied by the use of corrective tools (costs, fee reduction, substitution), the Court ensures that flexibility does not breed indiscipline. Arbitrators and parties know that breaching timelines will invite judicial scrutiny and potential penalty.

4. Prevents Tactical Manoeuvring: It closes a potential loophole where a party, aware of a looming deadline, could tactically delay proceedings to let the mandate expire and then challenge any subsequent award as a nullity, thereby derailing the entire process.

5. Aligns with Global Best Practices: The judgment brings Indian arbitration law in sync with the pragmatic, justice-oriented approach prevalent in advanced arbitration jurisdictions.

For Practitioners: Lawyers must be vigilant about statutory timelines and proactively seek extensions under Section 29A before the mandate expires. However, the judgment provides a crucial safety net. If an award is rendered late, the focus should shift immediately to filing a Section 29A(5) application, demonstrating "sufficient cause," and proactively suggesting terms (like cost penalties) to assuage the court’s concerns about condoning delay.

 X. Conclusion

The Supreme Court’s judgment in C. Velusamy v. K Indhera is a landmark that breathes practical wisdom into the procedural framework of arbitration. By holding that the court’s power to extend an arbitrator’s mandate survives even the rendering of a late award, the Court has fortified the foundational objective of arbitration: to achieve final and binding resolution of disputes. It acknowledges that while timelines are essential for efficiency, they are the servants of justice, not its masters. This ruling ensures that the arbitral process in India is robust, resilient, and capable of delivering on its promise as an effective alternative to conventional litigation.

Judgment Cited: C. Velusamy v. K Indhera, Civil Appeal No(s). of 2026 arising out of SLP (C) No(s). 6551 of 2025, Supreme Court of India, decided on February 3, 2026.

Post a Comment

0 Comments