In a judgment that brings much-needed clarity to a contentious area of arbitration law, the Supreme Court of India, on January 7, 2026, delivered a decisive verdict in Regenta Hotels Private Limited v. M/s Hotel Grand Centre Point & Others. The case, arising from a bitter family dispute that spilled over into a franchise agreement, became a battleground for interpreting critical provisions of the Arbitration and Conciliation Act, 1996 (the Act), particularly concerning interim injunctions and the crucial moment when arbitral proceedings are deemed to have "commenced."
The Court's ruling, authored by
Justice Augustine George Masih, with Justice Dipankar Datta concurring,
overturns the Karnataka High Court's order and reinstates an interim injunction
protecting a hotel's operations. More importantly, it authoritatively settles
the legal debate on the interpretation of Sections 9 and 21 of the Act, harmonizing
them with procedural rules. This deep dive unpacks the facts, the legal
labyrinth, and the profound implications of this landmark judgment for
businesses, legal practitioners, and the arbitration ecosystem in India.
Part 1: The Factual Quagmire – A Hotel, a
Franchise, and a Family Feud
The saga begins in the scenic
locale of Srinagar, Jammu & Kashmir, where Respondent No. 1, M/s Hotel
Grand Centre Point, operated a hotel. The hotel was owned by a partnership firm
consisting of four brothers (Respondents No. 2 to 5). Seeking to elevate its
business, the firm entered into a Franchise Agreement dated March 23, 2019,
with the appellant, Regenta Hotels Private Limited, a well-known hospitality
brand. Under this agreement, Regenta would lend its brand name, technical
expertise, and operational know-how.
Parallelly, the brother-partners
were embroiled in a family dispute over property rights, which was partially
settled by a Settlement Deed dated April 20, 2022. This deed gave Respondent
No. 5 operational control of the hotel for two years. Trouble began when Respondent
No. 2 allegedly started interfering with the hotel's daily operations—shouting
at staff, threatening to cancel bookings, and demanding separate payments outside
the franchise agreement.
To safeguard its brand and the
hotel's operations, Regenta approached the IXth Additional City Civil and
Sessions Judge, Bengaluru (Trial Court) on February 16, 2024, filing an
application (AA No.4 of 2024) under Section 9 of the Arbitration Act. They
sought interim injunctions to restrain Respondent No. 2 from causing
disruptions. The court granted an ad-interim injunction on February 17, 2024.
Subsequently, Regenta initiated
arbitration by sending a notice to all respondents on April 11, 2024, as per
Clause 19.1 of the Franchise Agreement. Respondent No. 2 replied on April 23,
2024, refusing arbitration and claiming he was not a signatory to the franchise
agreement. As the parties could not agree on an arbitrator, Regenta filed a petition
under Section 11 of the Act before the High Court on June 28, 2024, for the
appointment of a sole arbitrator.
Meanwhile, the Trial Court, after
hearing the parties, dismissed Regenta's interim applications (I.A. Nos. 5 to
7) on October 1, 2024. It held that Regenta failed to establish a prima facie
case, notably because they hadn't shown Respondent No. 2's consent to the
franchise agreement.
Regenta appealed to the High
Court of Karnataka. In its Impugned Judgment dated November 14, 2024, the High
Court made two key findings:
1.It rejected the Trial Court's
reasoning, holding that the franchise agreement was valid and the partners had
acquiesced to it from 2019 to 2023.
2.However, it upheld the
dismissal of the interim injunction on a different, procedural ground. It ruled
that as per Section 9(2) of the Act and Rule 9(4) of the Arbitration
(Proceedings Before the Courts) Rules, 2001, arbitral proceedings must commence
within 90 days (3 months) of an interim order. Since Regenta's Section 11
petition was filed on June 28, 2024 (over 90 days after the February 17
injunction), the High Court deemed the arbitration not commenced in time,
leading to the automatic vacation of the interim order.
Aggrieved by this interpretation,
Regenta approached the Supreme Court. The core legal question was simple yet
profound: When do arbitral proceedings "commence" for the purpose of
Section 9(2) of the Act?
Part 2: The Legal Crucible – Dissecting
Sections 9, 21, and Rule 9
The Supreme Court's analysis
forms the bedrock of this precedent. The Court meticulously examined the statutory
scheme, supported by a consistent line of its own judgments.
Legal Point 1: The Statutory Provisions – A
Textual Analysis
The Court first laid out the
relevant sections:
1. Section 9: Allows courts to
grant interim measures before, during, or after arbitral proceedings.
aSub-section (2) states: "Where, before
the commencement of the arbitral proceedings, a Court passes an order for any
interim measure... the arbitral proceedings shall be commenced within a period
of ninety days from the date of such order..."
b. Section 21 – The Heart of the
Matter: Defines commencement. "Unless otherwise agreed by the parties, the
arbitral proceedings in respect of a particular dispute commence on the date on
which a request for that dispute to be referred to arbitration is received by
the respondent."
c. Section 43(2): For limitation
purposes, an arbitration is deemed to have commenced on the date referred to in
Section 21.
d. Rule 9(4) of the 2001 Rules: A
procedural rule which states that if arbitral proceedings are "not
initiated within three months" from the date of a Section 9 application,
any interim order "shall stand vacated automatically."
The conflict arose from the High
Court's interpretation that "commencement" for Section 9(2) was
linked to the filing of a Section 11 petition before a court, not merely the
receipt of a notice under Section 21.
Legal Point 2: The Settled Jurisprudence –
Commencement is Defined by Section 21
The Supreme Court invoked a
formidable line of precedents to reinforce the primacy of Section 21:
1. Sundaram Finance Ltd. v.
NEPC India Ltd. (1999): Held that arbitral proceedings commence on the date
a request for arbitration is received by the respondent.
2. Milkfood Ltd. v. GMC Ice
Cream (P) Ltd. (2004): A three-judge bench affirmed this, noting the
formulation was deliberately adopted from the UNCITRAL Model Law. The Court
emphasized that Section 21 is not for limitation purposes alone but for
"other purposes also."
3. Geo Miller & Co. Pvt.
Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd. (2020): Reaffirmed that the
date of commencement is invariably the date of receipt of the notice invoking
arbitration, irrespective of subsequent procedural steps like a Section 11
petition.
4. Arif Azim Co. Ltd. v.
Aptech Ltd. (2024): A recent three-judge bench consolidated this principle,
stating that once a valid Section 21 notice is received, "commencement is
complete and effective for all legal purposes."
The Court crystallized the
principle: "The commencement of arbitral proceedings is a statutory
event defined exclusively under Section 21 of the Act." It is the receipt
of the request by the respondent that sets the proceedings in motion. Judicial
applications under Section 9 or Section 11 are consequential steps, not the
commencement itself.
Legal Point 3: Harmonizing Section 9(2)
and Rule 9(4) with Section 21
This was the Court's
masterstroke. The Respondent had argued that "commencement" in
Section 21 was only for calculating limitation under Section 43(2). The Court
rejected this as myopic.
The Court performed a harmonious
construction:
1.Objective of Section 9(2):
To prevent abuse—a party cannot obtain interim relief and then indefinitely
delay the arbitration. It ensures interim measures remain tethered to active
arbitration.
2.Role of Rule 9(4): The
Act itself does not specify consequences for missing the 90-day deadline. Rule
9(4) fills this gap by stating the interim order lapses automatically.
3.Linguistic Harmony: Rule
9(4) uses the word "initiated," while Section 9(2) uses "commenced."
The Court reasoned that in the context of the Act and the Rules framed under
it, these terms cannot be at odds. To give "initiated" a meaning
different from "commenced" would render Section 9(2)'s timeline
meaningless. Therefore, for the purpose of Rule 9(4), "initiated"
must be read as "commenced" under Section 21.
Thus, the 90-day/3-month clock
starts ticking from the interim order. The party must ensure the respondent
receives a request for arbitration (Section 21 notice) within this period.
Filing a Section 11 petition is not the trigger for commencement; it is a
remedial step if the arbitration process stalls after commencement.
Legal Point 4: Why the High Court's
View Was Flawed
The Supreme Court identified the
High Court's fundamental error: conflating the commencement of proceedings with
the judicial mechanism to appoint an arbitrator.
The Court held that treating the
date of the Section 11 petition as the date of commencement would:
1. Rewrite Section 21 sub
silentio, undermining legislative intent.
2. Create an "incoherent"
scheme where a party who has duly served a Section 21 notice could still be
non-compliant until they file a court petition.
3. Be "antithetical to the
flexibility and autonomy" of the Act, forcing parties to rush to court
even when contractual appointment procedures are ongoing or the respondent is
cooperating.
Part 3: Application to Facts and the
Final Ruling
Applying the settled law, the
Supreme Court found Regenta's actions timely:
a. Ad-interim injunction granted:
February 17, 2024.
b. 90-day deadline for
commencement: May 17, 2024.
c. Regenta's arbitration notice
(Section 21) served: April 11, 2024 (Received and replied to by Respondent No.
2 by April 23, 2024).
Conclusion: Arbitral
proceedings commenced on or before April 23, 2024, which was well within the
90-day statutory period from February 17. The subsequent filing of the Section
11 petition on June 28 was irrelevant for calculating commencement.
Therefore, the Supreme Court:
1.Set aside the Impugned Judgment
of the Karnataka High Court.
2.Set aside the Trial Court's
Order of October 1, 2024, which vacated the injunction.
3.Restored the Trial Court's
interim injunction Order of February 17, 2024, protecting Regenta's operational
rights pending arbitration.
4.Directed the High Court to
expeditiously decide the pending Section 11 petition for arbitrator
appointment.
5.Disposed of a related contempt
petition, noting the appeal's resolution.
Part 4: Implications and Conclusion – A Clear
Roadmap for Practitioners
The Regenta Hotels judgment is
a landmark with wide-ranging implications:
For Parties Seeking Interim
Relief:
1. Strategic Priority: The
moment you obtain a pre-arbitration interim order under Section 9, your
immediate, non-negotiable task is to formally invoke arbitration by serving a
clear notice under Section 21 on the respondent.
2. Diary the Deadline: The
90-day period is strict. Ensure proof of receipt (e.g., acknowledgment, email trail,
reply) dates within this period.
3. Section 11 Petition is
Secondary: You can work on appointing an arbitrator concurrently or
subsequently. A delay in filing the Section 11 petition, while not ideal, does
not per se cause the interim order to lapse if the Section 21 notice was
timely.
For Arbitration Practice:
a. Clarity and Certainty:
The judgment ends the confusion between "invocation" and
"commencement." It firmly anchors the legal moment of commencement to
the respondent's receipt of the notice.
b. Prevents Abuse: It
balances the need for urgent court protection with the obligation to proceed to
arbitration diligently, preventing tactical delays.
c. Upholds Party Autonomy:
By delinking commencement from court intervention, it respects the parties'
agreement to resolve disputes privately.
For the Indian Arbitration
Landscape:
This ruling strengthens India's
pro-arbitration jurisprudence by providing a predictable, principle-based
interpretation of the Act. It aligns Indian law with international best
practices (UNCITRAL Model Law) and reduces scope for procedural technicalities
to derail legitimate interim protections.
In conclusion, the Supreme
Court's decision in Regenta Hotels is a textbook example of judicial reasoning
that clarifies a complex procedural knot. It reinforces that in arbitration, as
in law, clarity of commencement is the beginning of a fair and efficient
resolution. By protecting the interim relief granted to Regenta, the Court has
also sent a strong message about safeguarding commercial operations from being
held hostage by internal disputes, ensuring that business continuity is not
sacrificed at the altar of procedural ambiguity.
Case Reference: Civil
Appeal No. of 2026 [Arising out of SLP (Civil) No. 30212 of 2024] with Contempt
Petition (Civil) No.189 of 2025 – Regenta Hotels Private Limited v. M/s Hotel
Grand Centre Point & Others, Supreme Court of India, decided on January 7,
2026.
0 Comments