The Embryo of a Contract: A Landmark Supreme Court Ruling on Letters of Intent and State Accountability

Supreme Court

1. In a significant judgment that clarifies the legal standing of government tenders, the Supreme Court of India, on November 24, 2025, delivered a verdict in the case of State of Himachal Pradesh & Anr. vs. M/s OASYS Cybermatics Pvt. Ltd. The ruling strikes a delicate balance between the State's freedom in contractual matters and the constitutional prohibition on arbitrary action. At its heart was a simple yet profound question: when does a government's promise become a legally binding contract? The Court’s answer provides crucial guidance for businesses, government departments, and legal practitioners navigating the complex world of public procurement.

2. The dispute originated from the Himachal Pradesh government's efforts to modernize its Public Distribution System (PDS) by introducing upgraded electronic Point-of-Sale (ePoS) devices with biometric and IRIS-scanning capabilities. This was a project of immense public importance, aimed at ensuring transparency in the distribution of subsidized food grains. The journey to find a vendor, however, was fraught with false starts. The State initiated four separate tendering exercises between 2021 and 2022. In the first three, either no bidder qualified, or the process was cancelled to avoid a "single-vendor" situation. Finally, in the fourth tender, M/s OASYS Cybermatics emerged as the sole technically qualified bidder.

3. After financial negotiations, the State issued a Letter of Intent (LoI) to OASYS on September 2, 2022. This LoI, however, was not an unconditional award. It was a "conditional communication" that required OASYS to fulfil several pre-requisites before a formal contract could be signed. These included compatibility testing of its devices with the National Informatics Centre (NIC) software, a live demonstration, and the submission of detailed cost breakdowns. The LoI explicitly stated that the "final award letter" would be issued only after the successful completion of these tasks.

4. For the next eight months, a flurry of correspondence ensued. The State department repeatedly directed OASYS to proceed with preparations, including pilot deployments and training. OASYS, in turn, invested heavily, manufacturing over 5,000 devices and setting up logistical support. However, the core preconditions of the LoI—the formal testing and certification by NIC—remained a point of contention. The situation was further complicated when a rival bidder, Linkwell Telesystems, complained that OASYS had suppressed past blacklisting incidents of a predecessor entity.

5. Suddenly, on June 6, 2023, the State issued a terse letter cancelling the LoI "with immediate effect," stating only that a fresh tender would be invited. The letter provided no reasons for this abrupt termination. OASYS challenged this cancellation in the Himachal Pradesh High Court, which ruled in its favour. The High Court found the cancellation arbitrary, noting that the State had continued to engage with OASYS for months and that the grounds for cancellation (the blacklisting complaint and alleged non-performance) were afterthoughts not mentioned in the cancellation letter. The High Court quashed the cancellation and directed the State to honour the Letters of Intent.

6. The State of Himachal Pradesh then appealed to the Supreme Court. The apex court's analysis revolved around two fundamental issues. First, what was the true legal nature of the Letter of Intent? Did it create enforceable rights for OASYS? Second, was the State's decision to cancel it, even if it had the power to do so, arbitrary and unfair?

7. On the first issue—the nature of the LoI—the Supreme Court's judgment is a masterclass in legal clarity. The Court delved into a well-established line of precedents, including Dresser Rand S.A. v. Bindal Agro Chem Ltd., to articulate a coherent doctrine. It held that a Letter of Intent is, in the ordinary course, a "precursor to a contract and not the contract itself." It is a "promise in embryo," signifying an intention to enter into a future contract, but it does not bind either party until specific conditions are met. The Court described it as the distinction between a "promise to make a promise" and a "promise performed." Only the latter is legally binding.

8. Applying this principle to the facts, the Court found the conditional nature of the LoI issued to OASYS to be "beyond doubt." The document itself laid out a sequential process: testing first, then demonstration, then a formal agreement. The Court emphatically stated that the LoI was never intended to be the contract itself. Consequently, it held that the LoI did not create any "binding or enforceable rights" in favour of OASYS. This finding was crucial, as it established that, at the time of cancellation, no concluded contract existed between the parties.

9. However, the Court did not stop there. It moved to the second, more nuanced issue: the legality of the cancellation. Even in the absence of a contract, the Court affirmed that the State's administrative power is not unfettered. It remains subject to the discipline of Article 14 of the Constitution, which forbids arbitrary State action. The Court's role, as established in landmark cases like Tata Cellular v. Union of India, is to review the decision-making process, not the decision itself, testing it against the touchstones of illegality, irrationality, mala fides, and procedural impropriety.

10. The Supreme Court acknowledged that the Cancellation Letter was "laconic" and devoid of reasons, which was a procedural lapse. It suggested that the High Court's finding of arbitrariness on this ground was not entirely misplaced. In an ideal scenario, the Court noted, the proper remedy would have been to send the matter back to the State authority to reconsider its decision after recording cogent reasons and giving OASYS a hearing. However, given that nearly two years had passed since the cancellation—and considering the urgent public interest in modernizing the PDS—the Supreme Court decided to itself evaluate the substantive justifications the State offered in court.

11. The State had proffered two main reasons for the cancellation: (i) the complaint about OASYS's alleged past blacklisting, and (ii) OASYS's non-compliance with the LoI's preconditions. The Supreme Court meticulously dismantled the first justification. It found that an identical complaint had already been dismissed by the High Court in a prior proceeding, a judgment the State had accepted. The State, as a continuing entity, could not oscillate its legal stance. On substance, the Court held that the tender clause only required disclosure of subsisting blacklisting as of the bid submission date. The alleged incidents were from a past period and concerned a different entity, and thus did not disqualify OASYS. The Court termed the State's reliance on this complaint "factually misplaced and legally untenable."

12. On the second justification—non-compliance—the Supreme Court found merit in the State's position. The record showed that despite repeated reminders, OASYS had not furnished the itemised cost breakdown as mandated and, crucially, had not completed the formal compatibility testing and live demonstration required by the LoI. The Court made a critical distinction that the High Court had overlooked: the difference between 'taking steps' and 'taking the right steps'. OASYS's actions in manufacturing devices and conducting training, while industrious, were "unilateral" and did not constitute compliance with the specific, stipulated preconditions. The Court called this "commercial impatience rather than contractual compliance."

13. Weighing these justifications, the Supreme Court concluded that the cancellation was not arbitrary. The State's growing concern about deploying uncertified devices that might not integrate with the national Aadhaar-enabled PDS was a "germane" concern, not a whimsical one. The Court also noted that the cancellation led to a fresh, open tender and not an award to a favoured bidder, negating any allegation of mala fides. Furthermore, the Court rejected OASYS's plea of "legitimate expectation," stating that the conditional terms of the LoI itself acted as an explicit disclaimer against any such clear and unambiguous assurance.

14. While allowing the State's appeal and setting aside the High Court's order, the Supreme Court demonstrated a remarkable sense of equity. Recognizing that OASYS had incurred costs on devices and work that the State might have used during pilot stages, the Court directed the State to conduct a fact-finding enquiry and reimburse OASYS for the verified costs and expenses on the principle of quantum meruit (meaning "as much as he deserves"). This reimbursement, however, was strictly for tangible assets or work actually appropriated by the State; the Court explicitly barred any claims for loss of profit or consequential damages.

15. The epilogue of the judgment serves as a powerful reminder of the human cost of procedural delays. The Court emphasized that the PDS is a lifeline for millions, and when such projects are derailed, the ultimate cost is borne by the most vulnerable citizens. It called upon all stakeholders—government, technical partners, and private participants—to execute welfare-centric procurements with greater "institutional coherence, foresight, and accountability."

16. In conclusion, the Supreme Court's judgment in State of Himachal Pradesh vs. M/s OASYS Cybermatics is a landmark ruling that brings doctrinal clarity to the often-murky waters of pre-contractual government communications. It firmly establishes that a conditional Letter of Intent is not a contract but a "promise in embryo," thereby protecting the State's necessary discretion in public procurement. Simultaneously, it reinforces that this discretion is not absolute and must be exercised in a non-arbitrary, reasoned manner. Most importantly, by ordering quantum meruit compensation, the Court has introduced a vital element of equity, ensuring that businesses that act in good faith on a State's inducement are not left with crippling losses. This balanced approach strengthens the framework of public procurement, ensuring it serves the dual masters of administrative efficiency and constitutional fairness.