The Supreme Court of India’s recent judgment in a dispute between a solar power developer and a nodal agency under the National Solar Mission provides a masterclass on several complex legal intersections. It delves into the enforceability of liquidated damages clauses in contracts involving public interest, the scope of judicial power to modify arbitral awards, and the distinct roles of courts under the Arbitration and Conciliation Act, 1996. This ruling is pivotal for contractors, public sector undertakings, and legal practitioners navigating the terrain of infrastructure and energy projects.
I. The Dispute: Solar Power, Delayed
Commissioning, and a Hefty Claim
The case originated from the Jawaharlal
Nehru National Solar Mission (JNNSM), a flagship government initiative to
promote green energy. NTPC Vidyut Vyapar Nigam Ltd. (NVVNL) was appointed as
the nodal agency to implement the mission. In this capacity, NVVNL entered into
a Power Purchase Agreement (PPA) on 24.01.2012 with M/s Saisudhir Energy Ltd.
(SEL). SEL agreed to set up and supply 20 MW of solar power at a concessional
tariff, with a strict commissioning deadline of 26.02.2013.
SEL failed to meet this deadline.
It commissioned 10 MW after a two-month delay (26.04.2013) and the remaining 10
MW after a five-month delay (24.07.2013). The PPA’s Clause 4.6 provided for liquidated
damages (LD) for such delays. For delays beyond three months, the clause
stipulated damages at ₹1,00,000 per MW per day. NVVNL invoked this clause,
leading to arbitration.
II. The Arbitral Tribunal’s Split Verdict
A three-member Arbitral Tribunal
delivered a split award:
a. Majority Award: Held
that while delay was admitted, NVVNL had not proven actual loss. It awarded a
token amount of ₹1.2 crores (approx. 20% of the performance guarantee),
rejecting NVVNL’s full claim.
b. Minority Award: Held
that the LD clause represented a genuine pre-estimate of loss. It would have
allowed NVVNL to encash bank guarantees worth ₹49.92 crores.
Dissatisfied, both parties
challenged the award under Section 34 of the Arbitration Act before the Delhi
High Court.
III. The High Court’s Journey: Modification
and Re-modification
A. Single Judge’s Order
(Section 34 Proceeding):
The Single Judge held that the
breach (delay) was admitted. Relying on Section 74 of the Indian Contract Act,
1872, and precedent, the judge held that in cases of breach, reasonable
compensation is payable even without proof of actual loss, but it cannot exceed
the stipulated amount. Considering the project’s 25-year lifespan, the judge
deemed a 50% reduction of the calculated LD (as per Clause 4.6) to be
“reasonable compensation.” Consequently, NVVNL was awarded ₹27.06 crores, to be
recovered by deducting ₹25 lakhs per month from SEL’s dues.
B. Division Bench’s Judgment
(Section 37 Appeal):
Both parties appealed. The
Division Bench agreed with the Single Judge’s foundational principles but re-calculated
the compensation. It applied a different interpretation of the LD clause’s
sliding scale and reduced the payable amount to ₹20.70 crores.
These cross-appeals brought the
matter before the Supreme Court, with both parties contesting the High Court’s
interventions.
IV. Core Legal Issues Before the Supreme Court
The Supreme Court framed and
resolved the following pivotal issues:
1.In a contract for a public
utility project, is the employer required to prove actual loss to claim
liquidated damages under Section 74 of the Contract Act?
2.Was the Single Judge’s
modification of the arbitral award (enhancing compensation from ₹1.2 cr to
₹27.06 cr) permissible under the limited scope of Section 34?
3.Did the Division Bench, in its
order under Section 37, exceed its jurisdiction by further re-calculating and
modifying the compensation determined by the Single Judge?
V. The Supreme Court’s Analysis and Ruling
1. On Liquidated Damages in Public Utility
Contracts & Proof of Loss
SEL’s primary contention was that
NVVNL, having invested no capital in the project, suffered no actual loss and
was thus entitled to no compensation. The Court firmly rejected this argument.
a. Admitted Breach: The
Court first established that SEL’s delay in commissioning was an admitted fact,
triggering Clause 4.6 of the PPA.
b. Section 74 of the Contract
Act: The Court invoked Section 74, which states that upon a breach of
contract, the aggrieved party is entitled to “reasonable compensation” not
exceeding the stipulated sum, “whether or not actual damage or loss is proved
to have been caused thereby.” Proof of exact loss is not a sine qua non.
c. Public Interest Character
of the Contract: The Court affirmed the High Court’s finding that the PPA
was not an ordinary commercial contract. It was executed under the JNNSM, a
national policy aimed at promoting green energy—a matter of public utility and
environmental interest. Citing its precedent in M/s Construction and Design
Services vs. DDA, the Court held that in public utility contracts, delay itself
can be presumed to cause loss (e.g., to public welfare, environmental goals).
The burden, therefore, shifts to the defaulting party to show that no loss
occurred or that the clause is penal.
d. Conclusion on this
Issue: The Court held that NVVNL was entitled to “reasonable compensation”
under Clause 4.6 read with Section 74. SEL failed to discharge its burden of
proving that the stipulated sum was a penalty or that no loss ensued from the
delay. The Single Judge was correct in principle to award compensation.
2. On Permissibility of Modification under
Section 34
SEL argued that the Single
Judge’s act of modifying the award and enhancing compensation constituted impermissible
merits review, exceeding the limited grounds under Section 34.
The Court referred to the Constitution
Bench decision in Gayatri Balasamy vs. ISG Novasoft Technologies Ltd., which
explicitly recognized a limited power of modification vested in the Section 34
court. This power can be exercised:
a. Where the award is severable.
b. To correct clerical or
computational errors.
c. Where modification flows
inevitably from the court’s determination on a point of law without a fresh
merits inquiry.
The Supreme Court held that the
Single Judge’s modification fell within this permissible zone. The Judge did
not re-appreciate evidence but applied the law (Section 74) to the admitted
facts (breach and Clause 4.6) to determine what constituted “reasonable
compensation.” This was a correction of a legal error (the Tribunal’s failure
to properly apply Section 74), not an appellate review of facts. Hence, the modification
under Section 34 was upheld.
3. On Division Bench’s Intervention under
Section 37
This was the crux of the Supreme
Court’s ruling and where it found error. The Court drew a sharp distinction
between the roles of courts under Section 34 and Section 37.
1. Nature of Section 37
Appeal: An appeal under Section 37 is not a second appeal on facts or law.
It is an appeal against the order of the Section 34 court. The scope is even
narrower. The court must only examine whether the Section 34 court exercised
its jurisdiction correctly, without perversity, arbitrariness, or exceeding its
limits.
2. Error of the Division
Bench: The Supreme Court found that the Division Bench, after rightly
agreeing with the Single Judge’s legal approach (need to balance equities and
award reasonable compensation), proceeded to recalculate the compensation
amount. It substituted its own “reasonable” figure (₹20.70 cr) for the Single
Judge’s “reasonable” figure (₹27.06 cr). The Division Bench identified no legal
flaw, perversity, or jurisdictional error in the Single Judge’s calculation; it
merely preferred a different interpretation of the LD clause’s gradation.
The Supreme Court held this was unwarranted.
Citing AC Chokshi Share Broker Pvt. Ltd. vs. Jatin Pratap Desai, it reiterated
that a Section 37 court cannot substitute its view for a plausible view taken
by the Section 34 court. The Division Bench’s recalculation was a merits-based
intervention that trespassed into an area where the Single Judge’s discretion,
exercised lawfully, was final.
VI. The Final Outcome
a. The Supreme Court set aside
the Division Bench’s modification of the compensation amount.
b. The Single Judge’s order
awarding ₹27.06 crores to NVVNL was restored.
c. Civil Appeals filed by NVVNL
were ALLOWED.
d. Civil Appeals filed by SEL
were DISMISSED.
VII. Key Takeaways and Implications
1.Public Utility Contracts are
Different: For projects involving public interest, environmental goals, or
utility services, courts are more likely to enforce liquidated damages clauses
without strict proof of actual loss. Delay itself may be construed as a public
loss.
2.The Shield of Section 74:
The judgment reaffirms the settled law under Section 74 of the Contract Act. A
stipulation for liquidated damages is not a penalty to be ignored; it is the upper
limit for “reasonable compensation.” The aggrieved party need not prove actual
loss, but the court can reduce the amount if it finds the stipulated sum
unreasonable.
3.Limited, But Existent,
Modification Power: The ruling confirms and relies on Gayatri Balasamy to
settle that Section 34 courts have a limited power to modify awards. This power
is not appellate but is tied to correcting awards based on legal defects
discernible within the narrow confines of Section 34.
4.The Section 37 Boundary is
Sacred: This is perhaps the most significant procedural clarification. The
Supreme Court has strictly delineated the boundary of Section 37. Appellate
courts must show extreme restraint. They cannot re-adjudicate the
reasonableness of a compensation quantum lawfully determined by the Section 34
court. Their role is only to check for jurisdictional errors in the Section 34
order.
5.Clarity for Contracting
Parties: Parties, especially in infrastructure and energy sectors, must
draft liquidated damages clauses with care. In public interest contracts, these
clauses will be given strong effect. A party in breach must be prepared to pay
substantial compensation, even in the absence of direct financial loss to the
other side.
Conclusion
The Supreme Court’s judgment
serves as a vital navigational chart in the often-turbulent waters of
arbitration law and contract enforcement. It balances the need to uphold
contractual sanctity and public interest in timely project completion with the
imperative to keep judicial intervention in arbitration within strictly defined
statutory limits. By curbing the appellate court’s reach under Section 37, the
ruling reinforces the finality of arbitral awards and the limited corrective
role of courts, a cornerstone of India’s arbitration ecosystem.
Judgment Name: M/s
Saisudhir Energy Ltd. vs. M/s NTPC Vidyut Vyapar Nigam Ltd. & Connected
Appeals (Civil Appeal Nos. 12892-12893 of 2024 with 12894-12895 of 2024),
Supreme Court of India, decided on January 30, 2026.

0 Comments